JXN Water

Priority Projects

Meaningful Partnerships with JXN Water

JXN Water at Work

JXN Water is working hard to ensure all Jackson residents have reliable access to clean, safe drinking water and sewer services. JXN Water is working on 13 priority projects that focus on fixing the City of Jackson’s drinking water system and 11 priority projects focused on fixing the sewer system. That’s 24 projects in the works!

Water crews are fixing leaks and main breaks that waste the water you need and cause water availability issues. Since February 2023, we’ve repaired nearly 600 leaks and opened 400 closed valves to improve water flow through the system. Our water crews are also repairing problems that cause sewer overflows. We’ve come a long way and we’re not done!

See some of the work we’re doing below!

In Progress
Priority Project Details

Chemical systems at plants and wells

Drinking Water Priority Project

Modernize the chemical feed systems at the water treatment plants to ensure optimized chemical dosing through automation and flow paced dosing. 

    Corrosion control

    Drinking Water Priority Project

    Complete the implementation of the Mississippi State Department of Health -approved corrosion control plan. 

      Chlorine system improvements at O.B. Curtis

      Drinking Water Priority Project

      Improve the safety and operation of the chlorination systems at all water facilities. 

      Distribution system study, analysis, and implementation

      Drinking Water Priority Project

      Develop and implement a plan to make the water distribution system resilient, sustainable, and reliable. Work will include the development of a computer model, analysis of alternatives, creating of an asset management system, and other actions that will lead to dependable delivery of water (volume and pressure) to all Jacksonians, all the time. 

        Intake Structure Repairs

        Drinking Water Priority Project

        Repair raw water intake facilities at O.B. Curtis and JH Fewell. 

          Resilient power plan

          Drinking Water Priority Project

          Evaluate all water facilities for the need for emergency or redundant power. 

          Restore full performance and designed redundancy to all treatment processes at OB Curtis and JH Fewell.

          Drinking Water Priority Project

          Evaluate performance and restore redundancy at treatment facilities (J.H. Fewell and O.B. Curtis as applicable) unit processes and pumps 

          • Membrane system 
          • Raw water pumping and screening 
          • Oxidation basins 
          • Rapid mix 
          • Flocculation and sedimentation 
          • Sludge removal 
          • Filters 
          • UV 
          • Transfer pumping 
          • High service pumping

          SCADA system improvements

          Drinking Water Priority Project

          Improve the data available to control processes, manage and operate systems (to include the distribution systems) through new sensors, software, and other technology. 

            Sludge assessment in all finished water storage facilities

            Drinking Water Priority Project

            Determine if there is any sediment in any finished water storage facilities and if so, develop and implement a plan to remove all sediment. 

              System stabilization and sustainability plan

              Drinking Water Priority Project

              Develop a long-term financially sustainable plan for the Jackson water system that ensures clean, safe, and affordable drinking water for all of Jackson. 

                Coming Soon
                Priority Project Details

                Annual Sewer Cleaning & CCTV Contract

                Sewer Priority Project

                Contract for annual sewer cleaning and CCTV, and complete 100 miles/year. Coordinate this annual cleaning and CCTV work with the prioritized Service Request Investigations below.  

                  Emergency Sewer Failures

                  Sewer Priority Project

                  Complete cleaning and closed-circuit television (CCTV) for the rehabilitation and/or replacement of the Emergency Sewer Failure locations 

                    Investigate Service Request Locations

                    Sewer Priority Project

                    Contract an annual investigation of sewer issues coming from the 2,200 Service Request locations and coordinate cleaning and CCTV with the Annual Sewer Cleaning & CCTV Contract above.  

                      Queens Area Sewer Rehabilitation Project

                      Sewer Priority Project

                      Rehabilitation of the sewers within the Queens Project Area 3-6 focusing on, but not necessarily limited to, dry weather Sanitary Sewer Overflow (SSO) reduction and point repairs to address sewer line collapses.  

                        Completed
                        Priority Project Details

                        Alternative water source plan

                        Drinking Water Priority Project

                        Develop a plan for emergency supply and distribution of potable and non-potable water if needed to meet water demand beyond the capability of the Jackson drinking water facilities.

                        Mill Street Sewer Rehabilitation Project

                        Drinking Water Priority Project

                        Re-route 2,200 linear feet of sewer that crosses a railroad (RR) yard, where the sewer line has collapsed underneath the RR tracks. A new sewer line will be constructed around the RR yard and the existing sewer line will be filled with flowable fill and abandoned in place.

                        O&M Contract

                        Drinking Water Priority Project

                        Develop an operation and maintenance contract for all Jackson drinking water facilities to include the water treatment plants, the wells, the storage tanks, and the distribution system. Award the contract to a qualified firm of a period of not less than five-years with renewal options. 

                        Savanna Peak Cell Lagoon Cells

                        Drinking Water Priority Project

                        Clean out the three peak flow lagoon cells at the Savanna WWTP.

                        Savanna WWTP 100 MGD Peak Flow Wastewater Pump

                        Drinking Water Priority Project

                        Replace the 100 million gallons per day (MGD) Peak Flow Pump that discharges flow from the Influent Pump Station to the Stormwater Lagoon cells.

                        Savanna WWTP Emergency Repairs/Replace Dewatering Equipment

                        Drinking Water Priority Project

                        Replace 54-inch line from inside Influent Pump Station to Headworks, replace return activated sludge (RAS) Pump # 2, and install permanent dewatering equipment to eliminate monthly cost for renting two belt filter presses.

                        Savanna WWTP Phase 1B Type 2 Improvements

                        Drinking Water Priority Project

                        Construct new septage/Fat, Oils, and Grease (FOG) receiving station, rehabilitate one screw pump at the Effluent Pump Station, add 6th secondary clarifier, add new dewatering equipment, add covered sludge storage facilities along with new waste activated sludge (WAS) storage tank, construct new gravity thickeners, address structural deterioration in Influent Pump Stations, and rehabilitate the 84-inch line from Sludge Lagoons to Pump Station.

                        Trahon WWTP Rehabilitation

                        Drinking Water Priority Project

                        Conduct a Comprehensive Performance Evaluation and a Composite Correction Program (CCP) for the Trahon WWTP. Implement the CCP as schedule permits. Make immediate repairs to maintain operations as needed.

                        West Bank Interceptor Rehabilitation

                        Drinking Water Priority Project

                        Complete the cleaning and rehabilitation of the West Bank Interceptor (WBI) for Project 6 Segment Phase (MH IT0118 to MH IT0136). This repair will address the low manhole that is believed to be a major contributing source of inflow during a river stage in excess of 26 ft. The project will also address any needed grouting work of the interceptor and manholes in the Country Club area of the WBI. Identify additional major river water inflow locations and defects causing significant volumes during a river stage above 26 ft. Develop and implement the repair plan, including a schedule of implementation.

                        Winterization of system

                        Drinking Water Priority Project

                        Complete all actions necessary to winterize all drinking water facilities and make them resilient to the impacts of freezing weather.